Quick answer: Usually yes. But it depends on your floor size, your headcount, and how much noise your work can absorb. Four delivery methods exist, and picking the wrong one costs you weeks.
City of Sydney allows noisy construction in the city centre only from 7am to 7pm, Monday to Friday, and 7am to 5pm on Saturday. No work is permitted on Sundays or public holidays. Outside the city centre, the window is open from 7.30am to 5.30pm on weekdays and 7.30am to 3.30pm on Saturday.
Compare that to your own office hours. The legal window for demolition, drilling, and wall framing sits almost exactly on top of the hours your team needs to work. That overlap is the whole problem.
CBD towers add a second layer. Restricted delivery windows and lift bookings push high-rise projects past suburban sites every time. Your builder competes with every other tenant for the goods lift and loading dock.

Your builder hoards off one zone, finishes it, moves staff in, then hoards the next.
Staging needs spare floor space. With 900 sqm and 60 desks, you can shuffle people around. With 180 sqm and 20 desks, you cannot. It also stretches the program, since every hoarding line means a second mobilisation and duplicate protection works.
The wet and dusty trades feel this most, since partition framing, plasterboard, ceilings, and painting all need clean handover between zones, and the same office partitions that create the hoarded zone during construction often become permanent meeting room walls afterward. Contractors like Pro Plaster N Paint, who handle partitioning, acoustic and fire-rated systems, suspended ceilings and painting across Sydney, deal with this sequencing constantly.
You lease short-term space and your builder gets an empty site running at full speed. You pay rent twice and move twice, but you buy back weeks of program and remove the daily productivity drag. For small tenancies with heavy demolition, decanting often works out cheaper once you price staff downtime honestly.
Trades start at 6pm and finish before 7am, so your team walks into a cleaned site each morning. This suits core drilling, demolition and ceiling grid removal. It fails as a whole-project strategy: every trade carries a loading, the Sunday ban removes a day, and night programs run longer and cost far more.
You accept a short shutdown, build hard, and reopen. For teams that can work remotely for two to four weeks, this is often the least disruptive option overall. The risk sits entirely on the completion date.
| Approach | Effect on Program | Cost | Daily Disruption | Best For | Main Risk |
| Staged fitout | Adds roughly 20 to 40% to construction | Moderate | High, lasts the whole build | Floor plates above ~600 sqm with spare desks | Staff patience wears thin by week four |
| Decant | Shortest construction phase | High: double rent, two moves | Two move days, then none | Small to mid tenancies, heavy demolition | Swing space lease misses the real handover date |
| After-hours | Extends program; no Sunday work | Highest per trade hour | Low in business hours | Targeted noisy tasks only | Trade fatigue, defects found late |
| Full vacate | Fastest calendar finish | Lowest construction cost | Total, then none | Teams that can work remotely 2 to 4 weeks | No fallback if handover slips |
Most Sydney projects end up as hybrids: a staged base program, demolition pushed after-hours, and a two-week decant only for the floor with the heaviest services work.
Continuity is decided in the six weeks before anyone picks up a tool.
| Item | Lead Time |
| In-stock chairs and standard desks | 2 to 4 weeks |
| Made-to-order local benching and joinery | 6 to 10 weeks |
| Imported European or US furniture | 10 to 16 weeks |
| Custom glass partitions | 3 to 5 weeks |
| Specialist or imported flooring | 4 to 6 weeks |
For a 10 to 14 week construction program, place furniture orders no later than week 2 to 4, and order imported pieces at design sign-off. Tenants who choose to move in late move into a finished space and sit on hired chairs for a month.
Landlord consent usually takes two to four weeks once you submit plans, contractor details and insurance certificates. Most Sydney buildings also require a Fitout Consent Application, reviewed in one to three weeks. Put both on the Gantt chart with a named person chasing them. Approvals sitting in an inbox are the cheapest delay to prevent.
Your business does not stop because a wall is unpainted. It stops because the phones went down. Map every cutover to a specific night, confirm it in writing with your provider, and build a rollback plan. Friday nights give you a weekend of margin.
Name the hours trades may enter occupied zones, the lift booking process, and who can approve a change to either. A verbal promise about noise does not survive a program slip.
Approval type varies with scope. A Development Application covers structural changes, heritage buildings and fire safety work. A Complying Development Certificate is the faster path for low-impact projects. An Occupation Certificate confirms compliance before you occupy.
Start with the date you must hand back the old space, not the date you want to move in. Make good obligations run in parallel with the new fitout and compete for the same budget and trades.
The gap between your new lease start and your make good deadline is your real buffer. If it is four weeks, a program with no float will cost you holdover rent.
The market gives tenants room to negotiate right now. Sydney CBD vacancy sits at 13.8%, and Parramatta rose to 23.5% in the six months to July 2026. Ask for a longer rent-free fitout period. Those weeks are worth more than a slightly better face rent.
Realistic timing: 12 to 24 weeks from brief to move-in. For 500 to 1,000 sqm, the on-site phase alone runs eight to fourteen weeks. Most delays land before installation begins, so that is where your attention belongs.

Staff handle disruptions they can predict. They resent disruption that surprises them.
Your team: publish the staged plan before hoarding goes up, showing which zone is hit in which week and where displaced people sit. Update it weekly. Flag high-noise days three business days ahead so people can move client presentations.
Your clients: share only entry changes, meeting room availability, and any period when reception relocates.
Assign one internal person as the single channel to the contractor. Continuity breaks when six managers each cut their own deal with the site foreman.
Base building surprises. Existing mechanical, structural and fire systems limit what is possible, and you learn the true condition only once ceilings come down.
Heritage buildings and full DA works. These approval durations resist any amount of parallel scheduling.
Imported specification signed off late. A European chair with a 16-week lead time approved in week 10 will not arrive by handover.
Each is manageable early, and none is manageable in week eight. Keep contingency in the program, not just the budget: two weeks of float across a fourteen-week phase is a sensible starting point.
Whether your business keeps running through a commercial office fitout depends on your situation. No single method wins for everyone.
Staging suits larger floor plates with spare desks. Decanting suits small tenancies facing heavy demolition. After-hours work suits targeted noisy tasks, not whole programs. A short full vacate suits teams that can work remotely.
One thing holds across all four. Sydney’s construction hours cap the working day, ban Sunday work, and sit on top of your trading hours. Your program has to bend around that.
Every decision that protects continuity happens before construction starts. Order long-lead items at design sign-off, treat approvals as dated activities, sequence the IT cutover deliberately, and put access hours in the contract. Then build backwards from your make good deadline and hold two weeks of float.
Often yes, but it depends on floor size. Staging works when you have spare desk capacity, usually above roughly 600 sqm. Small tenancies with heavy demolition normally need a short decant instead.
In the City of Sydney city centre, noisy work runs 7am to 7pm on weekdays and 7am to 5pm on Saturday. Elsewhere in the LGA, it is 7.30am to 5.30pm on weekdays and 7.30am to 3.30pm on Saturday. Sundays and public holidays are off limits without specific approval.
For some tasks, yes. Core drilling, demolition and ceiling grid removal suit the night shift. Running a whole fitout after hours is different: every trade carries a loading, the Sunday ban removes a day, and supervision gaps show up as defects later.
Plan for 12 to 24 weeks from brief to move-in. For 500 to 1,000 sqm, on-site construction alone runs eight to fourteen weeks. Staging an occupied site adds roughly another 20 to 40%.
Late ordering and late approvals. Imported furniture at 10 to 16 weeks and made-to-order joinery at 6 to 10 weeks are the usual culprits, followed by landlord consent sitting unreviewed for a fortnight.
Most internal fitouts qualify as exempt or complying development and only need a CDC. A full DA applies to structural changes, heritage buildings, fire safety alterations or a change of use. You need an Occupation Certificate before occupying either way.
Not always. Staging avoids double rent but adds duplicate mobilisations, hoarding and a longer program. Once you price staff downtime honestly, a short decant often comes out level or ahead for smaller tenancies.